The new building of the alltours corporate headquarters continues to take shape. On September 30, the official laying of the foundation stone for the building will take place on the 3.200 square meter property on the Düsseldorfer Mannesmannufer directly on the Rhine.
After the previous development had been torn down and the civil engineering and stabilization work that followed, the shell construction work for the new headquarters of the Düsseldorf tour operator began at the end of July. In the meantime, the foundations and the floor slab of the building can already be seen. The side walls of the underground car park from the old building were also anchored and partially renewed. The shell is expected to be completed in mid-2022. The building complex is scheduled to be completed by the end of the first quarter of 2023.